Ptarmigan pointe
205 Stewart Creek Rise

– February 2025 – Deck post install started, interior drywall completed (South Building). Framing completed, windows and doors installed (North Building)
– March 2025 – Framing and timber installation of exterior decks and balconies, interior finishing ongoing, cabinetry and countertop installation started (South Building). Roofing started, interior framing completed, gypcrete flooring pours ongoing (North Building)
– April 2025 – Deck topping, interior flooring and countertop installation (South Building). Ongoing mechanical and electrical rough-ins, roofing completed (North Building)
– May 2025 – Exterior siding installation, interior painting and mirrors (South Building). Insulation and drywall (North Building)
– June 2025 – Ongoing exterior siding work including window/door trim (South & North Buildings). Civil deep utilities installation including storm tank and site grading
– July 2025 – Shower glass, lighting fixtures installed (South Building). Ongoing carpentry finishing, cabinetry installation started (North Building). Overhead garage doors installed, asphalt driveway pours started
100 Palliser Lane


– Town of Canmore Council approves the redesignation of existing direct control district on May 7, 2024. Permitting and tendering in progress with construction to potentially begin in 2025
– Site Test Fit, Energy Modelling and Building Renderings complete – subject to change
– Prime Consultant – GGA Architecture
– Notice of Decision posted April 8, 2025. Construction expected to commence Q3 2025
Palliser Master Plan
– Areas 1 & 2 of Palliser Trail Area Structure Plan
– Master Plan conceptual scenarios and high level proformas completed
– Subdivision application process to commence Q3 2025
