205 Stewart Creek Rise

– December 2023 – Development Permit submitted

– March 2024 – Canmore Planning Commission approval and Notice of Decision

– May 2024 – Groundbreaking Ceremony and construction mobilization

– June 2024 – Completed excavation and formwork (South Building)

– July 2024 – Poured concrete foundation footings and ICF walls (South Building)

– August 2024 – Completed concrete foundation and commence wood framing (South Building)

– September 2024 – Continued wood framing (South Building) and completed excavation (North Building)

– October 2024 – Added roof trusses (South Building) and started foundation work (North Building)

– November 2024 – Completed wood framing (South Building), completed foundation (North Building), transformer installed

100 Palliser Lane

– Town Of Canmore Council approves the redesignation of existing direct control district on May 7, 2024. Permitting and tendering in progress with construction to potentially begin in 2025 

– Site Test Fit, Energy Modelling and Building Renderings complete – subject to change

– Prime Consultant – GGA Architecture

Palliser Master Plan

– Areas 1 & 2 of Palliser Trail Area Structure Plan

– Master Plan conceptual scenarios and high level proformas completed